What a change order has to say to get approved

Every construction loan funds against one document: the approved schedule of values. A change order is how that document gets amended — and until the lender has approved it, the new work is not fundable, no matter who signed it.

  • Two approvals: the contract changes, and the budget the loan funds against changes
  • The money has to come from a source named on the document
  • The real cost is usually a draw cycle, not a fee

A change order gets approved twice

A change order is a written amendment to the construction contract. Your general contractor writes it, you sign it, and between the two of you the scope and the contract sum have changed. That is the first approval, and it is the one most builders mean when they say the change order is done.

The loan runs on a second document. Every construction loan funds against an approved schedule of values — the line-item budget underwriting priced, cut and signed off on before closing. Draws release against percentages of completion on those lines, and the inspector who visits the site is reconciling work in place against that same list. Nothing outside it is fundable.

So the change order has to be approved twice: once by the parties to the contract, and once by the lender, which is being asked to amend a budget it underwrote and is lending against. A change order signed only by you and your contractor is a valid contract amendment and an unfunded one. The work can proceed. The money does not follow it.

What the lender needs on the document

Which lines move, and by how much

Not a description of the work — the lines. A change order that reads “additional foundation work, $18,400” tells the lender what happened and nothing about what to fund. The one that reads “footings and foundations, from $42,000 to $60,400” can be entered into the budget and inspected against. The document has to speak the schedule of values back to the lender.

The new contract sum

The total after the change, stated on the document rather than left to be worked out. Underwriting is checking it against the total project cost it approved and against the leverage caps that total produced. A change order with no new contract sum cannot be checked against anything, so it waits in a queue until someone asks for the number.

Where the money comes from

Every change order has a funding source, and there are only four: the contingency line, a reallocation from a line that came in under budget, your own cash, or an increase in the loan. The document has to name which one. This is the field that decides how fast the change order moves, and most of the ones that stall, stall here.

What it does to the completion date

If the work adds weeks, say so and say how many. Lenders read a change order against the maturity date as closely as against the budget. One that quietly pushes completion past the end of the term is an extension request wearing a different hat, and it gets handled as one — on the extension timetable, not the change order timetable.

Signatures and backup

Signed by the contractor and by you, with the subcontractor bid or quote for the new scope attached. A lump sum with nothing behind it reads as a contractor pricing against a captive budget, and underwriting treats it that way. One written bid is usually enough. The point is that the number came from somewhere outside the change order itself.

Whether the scope changes the appraisal

Adding finished square footage, a pool, a garage conversion — anything that changes what the finished property is — can invalidate the as-completed appraisal the loan was sized on. That is not a budget question. It is a re-appraisal, and it is the slowest kind of change order there is. Flag it yourself instead of letting the inspector find it in month six.

The four places the money can come from

A change order asks to spend money the approved budget did not have, so the first thing underwriting looks for is the source. There are four, and they are not interchangeable.

The contingency line is the fastest, because the money is already inside the approved budget and already inside the leverage cap. Nothing about the loan changes: one line goes up, contingency goes down, the contract sum is unmoved. The catch is that contingency has a gatekeeper. It exists for exactly this, and the lender decides what qualifies — so a change order drawing on it needs to be the kind of surprise contingency is for, not a finish upgrade you decided you wanted.

A reallocation is cheaper still. If a line came in under what it was budgeted at, that slack is real money sitting inside the schedule of values, and a change order can move it. The document nets to zero: one line up, another down, contract sum unchanged, loan unchanged, caps untouched. What it needs is a line with genuine slack — work that is complete or contracted at the lower number, not a line you expect to come in under.

Your own cash always works and never helps your leverage. You pay for the new scope outside the loan, the line gets added to the budget at your expense, and the lender may ask to see the funds before approving, because what it cares about is that the build finishes. This is the right answer for a modest overrun on a tight cap, and it is where most mid-build change orders end up.

An increase in the loan is the slowest and the least available. It means reopening the sizing: a new total project cost, both leverage caps recalculated against it, usually a new appraisal if the finished product changed, and a return trip through underwriting on a file that is already funded and drawing. Some programs will consider it. Many will not entertain it mid-build at all. Plan the change order around the other three and treat an increase as the exception.

Why a zero-dollar change order goes through first

The change orders that clear in days rather than weeks have one thing in common: they do not change the loan. Review effort is proportional to what the lender has to re-decide. A change order that nets to zero moves numbers inside a budget that was already approved, so one reviewer can enter it and the inspector picks it up on the next visit. A change order that moves the contract sum forces a re-check of both leverage caps. A change order that changes the finished product forces a new appraisal, and everything downstream of it waits.

So the practical skill is writing the change order as a reallocation whenever the numbers allow it — and that depends on knowing, mid-build, which of your lines have real slack. A builder who can show $6,400 of finished site work under budget has a funding source and a one-page document. A builder who only knows the job is roughly on track has to ask for money, which is a different request with a different answer.

This is the argument for tracking actual cost against the schedule of values line by line from the first draw, not at the end. The slack is only usable if you can prove it before you need it.

What sinks a change order

It arrives after the work is done. The inspector credits a line at the amount approved at the time the work was in place, so framing built under an unapproved change order funds at the old line. Retroactive approval happens, but it is a favor rather than a process, and this is the most common way a builder ends up personally carrying a cost that was fundable.

It describes the work instead of the lines. A narrative about soil conditions is useful background, but it is not a budget instruction. If nobody can tell which line to adjust, nobody adjusts one.

It has no funding source. A change order that increases the contract sum and says nothing about where the money comes from is read as a request for more loan, which is the slowest path and often a no. Naming the contingency or a reallocation turns the same request into an entry.

It crosses a cap. Leverage is limited as a share of total project cost and again as a share of as-completed value, and the lower one governs. A change order that pushes the budget past the binding cap cannot be funded from the loan at any speed. The answer there is cash or a smaller scope, and knowing which cap is binding tells you that before you submit.

It moves the finish date without saying so. A change order that adds six weeks to a build with eight weeks of term left is an extension conversation. Submitting it as a budget change does not avoid that conversation. It just delays it to a worse moment.

Example scenario: the change order that cost twenty-four days

Illustrative example. Numbers are hypothetical and not from a specific client or loan.

A builder is nine weeks into a spec build. The lot cost $100,000 and the approved schedule of values totals $412,000, so total project cost is $512,000 and the loan was written at 82 percent of it: $419,840, with $92,160 of his own money in the deal. The loan funds the build in draws against the approved budget.

At the footing stage the engineer requires a deeper foundation on one elevation after the soil report comes back with a soft layer. The foundation line goes from $42,000 to $60,400 — an extra $18,400 that nobody budgeted.

Two things are also true about his budget. Site clearing and fill was carried at $31,000 and finished at $24,600, so there is $6,400 of proven slack on a completed line. And the contingency line still has $12,000 in it.

So he writes the change order as three entries instead of one: foundation up $18,400, site work down $6,400, contingency down $12,000. New contract sum: $412,000, unchanged. The loan does not move, neither cap is touched, the finished house is the same house, and no new appraisal is needed. One reviewer approves it and the increase is reconciled on the next inspection.

The version he did not write is instructive. Submitted as “additional foundation work, $18,400, please increase the loan,” the file has to be re-sized: total project cost becomes $530,400, and 82 percent of that is $434,928 — an increase of $15,088 in loan proceeds, which leaves $3,312 of the overrun on him regardless. For that he would have gone back through underwriting on a funded, drawing loan, with a possible appraisal revisit, while the footing waited.

His change order still cost him something, and it was time. He submitted it four days before a scheduled draw; the review took six business days, so the foundation increase missed that draw and came through on the next one, twenty-four days later. The concrete sub wanted to be paid on his own terms, so the builder fronted the $18,400 out of pocket and waited three and a half weeks to be reimbursed by the loan. Nothing about the loan changed. His cash position changed for most of a month, in the middle of a build, which is exactly when it is least convenient.

PROCESS

How to write one that gets approved

STEP 01

Submit before the work starts, not after

The approval date is what the inspector credits against. Work in place ahead of an approved change order funds at the old line amount, and the gap is yours. If the trade cannot wait, say so on the document and ask what the lender needs to review it same-week.

STEP 02

Write it in the language of the schedule of values

Name the lines, give the old and new amount for each, and state the new contract sum. A reviewer should be able to enter your change order into the budget without calling you. That alone is often the difference between days and weeks.

STEP 03

Name the funding source on the document

Contingency, a reallocation from a specific completed line, your own cash, or a request to increase the loan. Pick one and say which. An unsourced increase is read as a loan request, and that is the slowest version of every change order.

STEP 04

Look for a reallocation before you ask for money

Go line by line through what is complete and what is contracted, and find the slack. A net-zero change order is approved on a different track from one that moves the contract sum, because the lender has nothing to re-underwrite.

STEP 05

Attach the bid

A subcontractor quote or invoice for the new scope, from outside the change order. It answers the question underwriting is actually asking, which is whether the number is a price or a preference.

STEP 06

Say what it does to the schedule

Added days, stated plainly, and measured against the maturity date rather than against the original plan. If the change pushes completion past the term, raise the extension in the same conversation instead of a month later, with payments current.

How we fit

We are a private money loan broker. We arrange business-purpose real estate financing through a panel of third-party lenders and we are not a lender ourselves. Because we place files across that panel, we see how differently the same change order gets handled — which programs will reallocate inside an approved budget without ceremony, which require a construction management review on every amendment, and which will not reopen a loan amount mid-build under any circumstances. We also build ground-up ourselves, so the twenty-four-day version of this is one we have financed out of our own account.

Mid-build and facing an overrun?

Send the schedule of values and the change order. We will tell you whether it is a reallocation, a cash item or a loan conversation before you submit it. Three minutes, no credit pull.

One Bridge Capital arranges business-purpose real estate financing through a panel of third-party lenders and is not a lender. Terms shown are typical ranges, vary by lender, property and borrower profile, and are not a commitment to lend. Loans are for business purposes only and are not available for owner-occupied primary residences.

QUESTIONS

Frequently asked

It is a written amendment to both the construction contract and the approved schedule of values the loan funds against. It names the budget lines that move, the new amounts, the new contract sum and where the money comes from. Until the lender approves it, the amended work is not fundable, even with the contractor and borrower signatures already on the page.